Like every year, the SNCF takes advantage of the summer period to carry out major works on its Transilien lines, taking advantage of the drop in ridership. In 2025, several lines will be particularly affected, with total or partial interruptions to traffic, often on evenings or weekends. These changes are necessary to modernize infrastructure, improve network reliability and prepare for the arrival of new rolling stock, but they often annoy users!
Especially as the metro and RER are particularly affected this summer! So you'll need to plan ahead, anticipating line closures to find alternative solutions. In general, replacement buses and itineraries are proposed to those who use these lines on a daily basis, to limit inconvenience. Discover below the scheduled dates for Transilien line closures this summer, with more details to follow at the end of June.
In the Bruyères-sur-Oise sector, SNCF Réseau is modernizing the railway infrastructure by renewing switches and tracks.
Located in the 17th arrondissement of Paris, the Souverains railway bridge dates back to 1868, and part of its deck needs to be replaced. To limit the worksite footprint and free up tracks for Paris Saint-Lazare trains, the new decks will be installed from beneath the bridge, from the RER C tunnel.
Track and ballast maintenance and renewal work will be carried out in the vicinity of the Bois Colombes and Argenteuil stations, to enhance network reliability.
A railway bridge dating back to 1894 is currently being replaced at Saint-Denis, on the Northern Paris axis. This is the 3rd stage of the project: following the installation of the support structures in autumn 2024 and the launching of the new bridge in February, work is now focusing on the installation of the new track, catenary and rail signalling systems.
At Vaires-sur-Marne, 4 switches will be replaced on line P.
The second project will be carried out at La Ferté Milon, where 17 km of rails will be renewed:
Between Verneuil-l'Etang and Longueville, 13 km of track will be replaced by a factory train called "BOA".
This summer, work will focus on Livry-sur-Seine, where track and ballast will be replaced. Some work remains to be done, notably on the platform at Fontaine le Port.
The Villeneuve Saint-Georges Technicentre is undergoing a major transformation. Work is underway to construct new buildings and accesses to the north and south of the site.
Transport in Paris and Île-de-France: summer 2026 works on the metro, RER and tramway
As every summer, public transport in Paris and Île-de-France will be disrupted due to major modernization works. Unfortunately for users, these works are expected to affect the metro, RER, and tramway. Check out the detailed schedule and dates for these works, which are planned for June, July, and August 2026 on the RATP and SNCF networks. [Read more]



Transport in Paris and Île-de-France: summer 2026 works on the metro, RER and tramway